Relationship Among Shanghai World Expo Project Complexity,Time Limit and Human Cost
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    以世博AB片区建设项目为例,基于任务和组织视角,借助仿真软件ProjectSim分别模拟了任务并行、任务分包、组织结构优化及组织成员优化4种情景下项目复杂性与工期和人力成本的关系,认为项目复杂性与工期和人力成本在某些情况下并不冲突.通过在关键职位增加相关人员可以使得项目复杂性、工期和人力成本三者得到同步优化.

    Abstract:

    The Shanghai Expo AB area construction project was taken as an example to discuss the relationship of project complexity and time limit for it, and human cost under the four scenarios of parallel, sub contract, organization structure and members optimization by means of the simulation software ProjectSim. It is concluded that in some cases there are no conflicts between the project complexity, time limit and its human cost, and that all of them can be optimized simultaneously through increasing relevant personnel on key positions, which is totally different from the traditional view that time limit is often in conflict with human cost.

    参考文献
    相似文献
    引证文献
引用本文

何清华,罗岚,李永奎,陆云波.世博项目的复杂性与工期和人力成本关系[J].同济大学学报(自然科学版),2012,40(11):1742~1746

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2011-09-27
  • 最后修改日期:2012-09-24
  • 录用日期:2012-04-16
  • 在线发布日期: 2012-11-27
  • 出版日期:
文章二维码