Abstract:Based on the fabrication length of main cable and hangers and the installation location of cable clamps, the lower end force matrix of hanger was established, and independent equilibrium equations of temporary system were established for each construction stage. Multisegment twoforce bars considering gravity and multistage spatial catenary were respectively employed to simulate bidirectional sag characteristics of spatial cables, and two analytical methods were proposed for construction processes during hoisting girder. The proposed methods can separately solve the physical effect of any construction stages, without depending on the effect of any previous stages. The example shows that the proposed methods can rapidly respond to the realtime changes of construction state, and are very suitable for the realtime monitoring of construction process and technical decision analysis.