Abstract:Combining the study of resourceconstrained projectscheduling problem with the demand of construction schedule management in real projects, this paper integrates a hybrid algorithm with generalized precedence relations (GPRs) scheduling model, and then proposes better solutions for resourceconstrained schedule management. The hybrid algorithm presents crossover and mutation operations from differential evolution (DE) with artificial bee colony (ABC) to balance exploration and exploitation phases of the optimization process. Furthermore, the proposed model applies a serial method with generalized precedence relations to reflect individualvector priorities into the task schedule to calculate project duration. In order to generalize the use of most realworld construction projects, the resourceconstrained schedule management contains some methods by calculating critical paths, applying resource leveling of noncritical tasks, using correlation analysis to tradeoffs between time and cost of critical tasks. In the eclipse environment of Java programming language, it could obtain stable and accurate results, which project managers may use to make optimal decisions by resource constrained schedule, resource allocation, the optimized schemes of resources and duration.