Multi-objective Track Maintenance Plan Model and Solution
CSTR:
Author:
Clc Number:

U216

  • Article
  • | |
  • Metrics
  • |
  • Reference [12]
  • |
  • Related [20]
  • | | |
  • Comments
    Abstract:

    In order to solve the multi-objective model of track maintenance plan, the fast and elitist non-dominated sorting generic algorithm (NSGA-II algorithm) is improved through coding improvement, constraint condition control in the whole process and self-adaption of genetic coefficients. It can maintain the diversity of the population in solving the multi-objective problem of track maintenance to avoid premature convergence, the global optimal solution is obtained by accelerating convergence at the later stage. These methods solve the decisionmaking problem of large maintenance machineries’ optimal operation time and place. Case in Shanghai and Kunming line shows, established planning method has high computational efficiency and the effect of maintenance plan is obvious, the track irregularity of all sections did not exceed the limit of maintenance.

    Reference
    [1] 韩晋, 杨岳, 陈峰,等. 基于非等时距加权灰色模型与神经网络的轨道不平顺预测[J]. 铁道学报, 2014(1):81-87Han J, Yang Y, Chen F, et al. Prediction of track irregularity based on non-equal interval weighted grey model and neural network[J]. Journal of the China Railway Society, 2014, 36(1):81-87.
    [2] Albin Johnsson.Vibration dynamics of high speed train with Pareto optimized damping of bogie suspension to enhance safety and comfort[ J] . Journal of Geology, 2010 , 27 ( 4 ) : 276 ~285
    [3] 李雪,吴俊勇,杨媛,严翔,刘晓民,徐伟燕.高速铁路接触网悬挂系统维修计划的优化研究[J].铁道学报,2010,32(2):2237~44Xue L I, Jun-Yong W U, Yuan Y, et al. Research on Optimization of Catenary System Maintenance Schedule for High-speed Railways[J]. Journal of the China Railway Society, 2010, 50(12):2237-44.
    [4] 张英贵,雷定猷,汤波,王新宇.铁路客运站股道运用窗时排序模型与算法[J].铁道学报,2011,33(1):1~7Zhang Y G, Lei D Y, Bo T, et al. Due Windows Scheduling Model and Algorithm of Track Utilization in Railway Passenger Stations[J]. Journal of the China Railway Society, 2011, 33(1):1-7.
    [5] 张宝安,陆正刚,唐辰.高速动车组车轮型面多目标优化镟修[J].同济大学学报(自然科学版),2013,41(3):437~442Zhang B, Zhenggang L U, Tang C. Wheel Reprofiling of High-speed EMU Based on Multi-objective Optimization Strategy[J]. Journal of Tongji University, 2013, 41(3):437-442.
    [6] 易思蓉,张家玲.基于智能CAD系统的铁路选线方案多目标综合评价方法[J].铁道学报,2000,22(Z1):95~101Si rong Y I, Zhang J L. The multiple objective decision making for evaluating railway location schemes based on intelligent CAD system[J]. Journal of the China Railway Society, 2000.
    [7] 沈峰,杨晓光.多目标城市道路交叉口信号配时优化算法研究[J].同济大学学报(自然科学版),2009,37(7):898~902 Shen F, Yang X. Research on multi-object optimization algorithm of urban road traffic lights[J]. Journal of Tongji University, 2009, 37(7):898-902.
    [8] Quiroga, L, Schnieder E. Modelling of high speed railroad geometry ageing as a discrete-continuous process[J]. 2010.
    [9] 三和,雅史, 内田,雅夫. 軌道状態推移モデルの設定と軌道保守施策決定法 (特集 軌道技術)[J]. Rtri Report, 1997, 11.
    [10] 王建西,李海锋,许玉德.基于概率分布推移变化的铁路轨道几何状态评价与预测方法[J].中国铁道科学,2008,29(5):31~34Wang J, Li H, Xu Y. Evaluation and prediction method for railway track geometric state based on probability distribution change[J]. China Railway Science, 2008, 29(5):31-34.
    [11] 马迪. 我国高速铁路无砟轨道经济性研究[D]. 西南交通大学,2009.Ma Di. Study of economical efficiency for the ballastless track of high-speed railway in our country[D]. Southwest Jiaotong University,2009
    [12] 宋昕,黄磊.基于改进NSGA-Ⅱ算法的港口堆位分配问题研究[J].计算机工程与应用,2012,48(33):34~39SONG Xin. Study on port stack-scheduling based on improved NSGA-Ⅱ[J]. Computer Engineering\s \sapplications, 2012.
    Cited by
    Comments
    Comments
    分享到微博
    Submit
Get Citation

XU Yude, LIU Yiming, SHEN Jianfeng, QIU Junxing. Multi-objective Track Maintenance Plan Model and Solution[J].同济大学学报(自然科学版),2018,46(07):0926~0933

Copy
Share
Article Metrics
  • Abstract:1193
  • PDF: 910
  • HTML: 502
  • Cited by: 0
History
  • Received:October 19,2017
  • Revised:April 11,2018
  • Adopted:March 12,2018
  • Online: August 08,2018
Article QR Code